Key speciality contractors from design and construction were integrated into the project very early on, which resulted in a more efficient design that both reduced cost and accelerated the schedule. The structural steel was fabricated and erected $7.2 million under budget and 6 weeks ahead of schedule. The erection was completed with zero change orders and one quarter of the typical number of RFI’s.